MERALCO OPENS BIDDING FOR 900 MW BASELOAD POWER SUPPLY STARTING 2031

​PASIG, Philippines — The Manila Electric Company (Meralco) announced on Tuesday, September 29, that it has launched a Competitive Selection Process (CSP) to procure up to 900 megawatts (MW) of additional baseload power starting in 2031.

​The power distribution utility is inviting generation companies (GenCos) to submit their expressions of interest by October 15. A pre-bid conference is scheduled for November 6, while the deadline for bid submissions has been set for December 9.

Under the procurement terms, the winning supplier will enter into a 15-year power supply agreement. The contract entails providing an initial 600 MW starting February 26, 2031, followed by a second tranche of 300 MW a year later.

The resulting deal will be submitted to the Energy Regulatory Commission (ERC) for approval.

This new procurement round follows Meralco’s recent 600-MW supply auction intended for delivery starting in late February 2028 and 2029.

That contract was awarded across three generation firms:

  • ​Mariveles Power Gen Corporation (MPGC): The San Miguel Corporation (SMC)-led firm submitted the lowest bid of ₱5.3573 per kilowatt-hour (kWh) for 200 MW.
  • ​Sual Power Inc. (SPI): The SMC affiliate secured 200 MW with a bid of ₱5.4357 per kWh.
  • ​GNPower Mariveles Energy Center (GMEC): The Aboitiz-owned company claimed the final 200 MW at ₱5.5789 per kWh after scaling down its initial offer for the entire 600-MW capacity.